Grupa Azoty becomes CEE’s first company to offer fully biodegradable plastics

Grupa Azoty S.A. has launched a pilot line for the production of thermoplastic starch, with a capacity of 300,000 per year. The company has also signed cooperation agreements with Polska Grupa Opakowaniowa Opakomet S.A. and the Forestry Research Institute, as well as a letter of intent with the State Forests National Forest Holding. The signing of the documents, confirming the high business potential of the solution, took place at the Grupa Azoty Research and Development Centre in Tarnów on May 11th 2021.

11.05.2021
Reappointment of Grupa Azoty Management Board Members for new term of office

At its meeting held on April 19th 2021, the Supervisory Board of Grupa Azoty S.A. reappointed members of the Company’s Management Board for a new 12th term of office, with effect from May 18th 2021.

21.04.2021
Grupa Azoty Group posts solid financial results despite ongoing pandemic

In 2020, the Grupa Azoty Group posted consolidated revenue of PLN 10.5bn, delivering EBITDA of PLN 1.3bn, EBITDA margin of 12.6% (unchanged year on year) and net profit of PLN 355m.

15.04.2021
The project "Polimery Police" at its halfway point

50% of material progress was achieved by the largest investment of the Polish chemical industry - the "Polimery Police" project.

23.03.2021
Closing of debt financing for the Polimery Police project

On February 25th 2015, Grupa Azoty Polyolefins S.A. received a confirmation from Bank Pekao S.A., acting as the Facility Agent, that the conditions precedent under the Credit Facilities Agreement had been fulfilled. As a result, Grupa Azoty Polyolefins S.A. may now, subject to specific conditions for the first drawdown on each Facility and additional conditions for each disbursement, which do not differ from standard terms and conditions applicable to similar financing arrangements, apply for disbursement of funds under the Credit Facilities to finance the Polimery Police project. Thus, the last stage of the process to raise debt financing for the project has been successfully completed.

10.03.2021
Key piece of equipment for Polimery Police plant arrives at construction site

Between the late hours of Monday and early hours of Tuesday, a 96-metre-tall propane-propylene splitter was safely transported to the construction site of the Polimery Police plant. The logistic operation was successfully completed after almost four hours, marking the achievement of a key project milestone.

23.02.2021